01 — POWER DISTRIBUTION
Two independent paths, zero single points of failure
The facility is fed by two separate medium-voltage lines coming from different substations. Each line runs, physically separate, all the way to the rack with its own transformer, switchboard group, UPS system and PDU; even if one of the A and B paths is under maintenance or has failed, your racks continue to be powered at full capacity from the other path.
Automatic transfer (ATS) and static transfer (STS) switches change over between sources within milliseconds. All switchboards are metered; energy consumption is monitored and reported per rack.
- Grid
- 2 × MV lines · separate transformers
- Topology
- 2N (A+B) distribution
- Transfer
- ATS / STS < 10 ms
- IT capacity
- 1.2 MW (Phase 1)
- Rack feed
- A+B smart PDU
- Monitoring
- Per switchboard & rack
The A and B paths are physically separate; the failure or maintenance of a single component does not interrupt the power to the rack.